Parameter Detail: ICE-14(run 5)

start date (GMT) 2009-01-30 (30)
end date (GMT) 2009-01-30 (30)
degree of supercooling 0.80
crystalization cell temperature [degC] 3.02
nucleation cell temperature (pre nucleation) [degC] 10
nucleation cell temperature (nucleation start) [degC] -10
nucleation cell temperature (laten heat release) [degC] -4
nucleation cell temperature (post nucleation) [degC] 0
control time (stabilization start) 20:26:44
control time (nucleation start) 21:52:10
control time (laten heat release) 21:53:13
control time (crystalize start) 22:02:20
control time (melt start) 22:03:40
control time (melt end) 22:06:40
control duration (stabilization) 01:25:26
control duration (nucleation) 00:01:03
control duration (crystalization) 00:10:10
control duration (observation) 00:01:20
control duration (total) 00:14:30
note