start date (GMT) |
2008-12-19 (354) |
end date (GMT) |
2008-12-19 (354) |
degree of supercooling |
0.07 |
crystalization cell temperature [degC] |
3.75 |
nucleation cell temperature (pre nucleation) [degC] |
10 |
nucleation cell temperature (nucleation start) [degC] |
-10 |
nucleation cell temperature (laten heat release) [degC] |
-2 |
nucleation cell temperature (post nucleation) [degC] |
3.75 -> 5 |
control time (stabilization start) |
02:19:21 |
control time (nucleation start) |
03:33:20 |
control time (laten heat release) |
03:34:10 |
control time (crystalize start) |
03:49:30 |
control time (melt start) |
05:08:00 |
control time (melt end) |
05:14:00 |
control duration (stabilization) |
01:13:59 |
control duration (nucleation) |
00:00:50 |
control duration (crystalization) |
00:16:10 |
control duration (observation) |
01:18:30 |
control duration (total) |
01:40:40 |