Parameter Detail: ICE-11(run 3)

start date (GMT) 2009-01-05 (5)
end date (GMT) 2009-01-05 (5)
degree of supercooling 0.50
crystalization cell temperature [degC] 3.32
nucleation cell temperature (pre nucleation) [degC] 10
nucleation cell temperature (nucleation start) [degC] -10
nucleation cell temperature (laten heat release) [degC] -12.5
nucleation cell temperature (post nucleation) [degC] 0
control time (stabilization start) 20:18:00
control time (nucleation start) 21:18:55
control time (laten heat release) 21:30:50
control time (crystalize start) 21:31:05
control time (melt start) 21:34:30
control time (melt end) 21:38:04
control duration (stabilization) 01:00:55
control duration (nucleation) 00:11:55
control duration (crystalization) 00:12:10
control duration (observation) 00:03:25
control duration (total) 00:19:09
note