Parameter Detail: ICE-15(run 3)
| start date (GMT) | 2009-01-26 (26) |
|---|---|
| end date (GMT) | 2009-01-26 (26) |
| degree of supercooling | 0.90 |
| crystalization cell temperature [degC] | 2.92 |
| nucleation cell temperature (pre nucleation) [degC] | 10 |
| nucleation cell temperature (nucleation start) [degC] | -10 |
| nucleation cell temperature (laten heat release) [degC] | -4.6 |
| nucleation cell temperature (post nucleation) [degC] | 0 |
| control time (stabilization start) | 22:06:08 |
| control time (nucleation start) | 23:08:24 |
| control time (laten heat release) | 23:09:25 |
| control time (crystalize start) | 23:18:10 |
| control time (melt start) | 23:19:16 |
| control time (melt end) | 23:22:24 |
| control duration (stabilization) | 01:02:16 |
| control duration (nucleation) | 00:01:01 |
| control duration (crystalization) | 00:09:46 |
| control duration (observation) | 00:01:06 |
| control duration (total) | 00:14:00 |
| note |