Parameter Detail: ICE-04(run 2)
| start date (GMT) | 2008-12-19 (354) |
|---|---|
| end date (GMT) | 2008-12-19 (354) |
| degree of supercooling | 0.07 |
| crystalization cell temperature [degC] | 3.75 |
| nucleation cell temperature (pre nucleation) [degC] | 10 |
| nucleation cell temperature (nucleation start) [degC] | -10 |
| nucleation cell temperature (laten heat release) [degC] | -2 |
| nucleation cell temperature (post nucleation) [degC] | 3.75 -> 5 |
| control time (stabilization start) | 02:19:21 |
| control time (nucleation start) | 03:33:20 |
| control time (laten heat release) | 03:34:10 |
| control time (crystalize start) | 03:49:30 |
| control time (melt start) | 05:08:00 |
| control time (melt end) | 05:14:00 |
| control duration (stabilization) | 01:13:59 |
| control duration (nucleation) | 00:00:50 |
| control duration (crystalization) | 00:16:10 |
| control duration (observation) | 01:18:30 |
| control duration (total) | 01:40:40 |
| note |