Parameter Detail: ICE-01(run 5)
| start date (GMT) | 2008-12-23 (358) |
|---|---|
| end date (GMT) | 2008-12-24 (359) |
| degree of supercooling | 0.03 |
| crystalization cell temperature [degC] | 3.79 |
| nucleation cell temperature (pre nucleation) [degC] | 10 |
| nucleation cell temperature (nucleation start) [degC] | -10 |
| nucleation cell temperature (laten heat release) [degC] | -7.45 |
| nucleation cell temperature (post nucleation) [degC] | 3.79 |
| control time (stabilization start) | 23:46:52 |
| control time (nucleation start) | 04:16:26 |
| control time (laten heat release) | 04:17:56 |
| control time (crystalize start) | 04:39:39 |
| control time (melt start) | 05:19:22 |
| control time (melt end) | 05:22:04 |
| control duration (stabilization) | 04:29:34 |
| control duration (nucleation) | 00:01:30 |
| control duration (crystalization) | 00:23:13 |
| control duration (observation) | 00:39:43 |
| control duration (total) | 01:05:38 |
| note |